A customer has purchased a FlashArray//XL. What power cables are required in order to connect this array to rack PDUs?

  • A. 2 x C13/14
  • B. 4 x C13/14
  • C. 4 x C19/20


Answer : C

Which I/O card type is compatible across all FlashArray models?

  • A. 10GBaseT
  • B. iSCSI
  • C. FC


Answer : C

If a Technical Support Engineer (TSE) is not available to perform health checks after an installation, what action should the Implementation Engineer take?

  • A. Email the account team.
  • B. Update and close the case.
  • C. Verify that Remote Assist (RA) is open and update the case.


Answer : C

What command should be used to check the shelf cable connections?

  • A. purearray list --shelf
  • B. purehw list --enclosures
  • C. storage_view.py config


Answer : C

Upon completion of a hardware upgrade activity, which command should be used to unset the maintenance tag?

  • A. purealert tag --cancel
  • B. purealert untag --maintenance
  • C. purealert --unset


Answer : B

What are the interface names for a 4-port FC card in slot 1 in an XR2/3 array?

  • A. FC0, FC1, FC2, and FC3
  • B. FC4, FC5, FC6, and FC7
  • C. FC5, FC6, FC7, and FC8


Answer : B

In a situation where FC cards need to be re-used during a controller upgrade, which is a valid transfer path?

  • A. M > XR2
  • B. M > XR2/3
  • C. XR2 > XR3


Answer : B

Which default speed FC SFPs are shipped in FlashArray//XCR4 FC arrays?

  • A. 16
  • B. 32
  • C. 64


Answer : B

A FlashArray arrives with Purity 5.3.8 applied out of the factory. The account team requests that the array configured with Purity 6.1.21. Which steps should the Implementation Engineer select to meet this requirement?

  • A. Create a bootable USB stick from the 6.1.21 ISO file and reimage both controllers with it.
  • B. Copy the PPKG and SHA1 files to a USB stick and upgrade the controllers.
  • C. Configure the array with the current code and then open a case with Support to upgrade.


Answer : B

What is the maximum number of DirectFlash Shelves supported for FlashArray//XL?

  • A. 2
  • B. 3
  • C. 4


Answer : A

Before installing array rails, where should the cage nuts be placed?

  • A. Lowest square of lowest RU
  • B. Lowest square of top RU
  • C. Top square of the lowest RU


Answer : A

What is the speed of the Ethernet ports to connect a FlashArray //E to a DFS?

  • A. 40G
  • B. 25G
  • C. 100G


Answer : C

What command will view NVRAM install and update status?

  • A. purearray list
  • B. puredrive list
  • C. purehw list --all


Answer : C

When executing a FlashArray upgrade from the FA-405 to a FA-X Series, into which slot on CT1 must the 2 Port InfiniBand Card be installed?

  • A. 0
  • B. 2
  • C. 3


Answer : C

An Implementation Engineer is scheduled to install a FlashArray and a DirectFlash Shelf (DFS).
What action should the Implementation Engineer perform?

  • A. Refer to the “Recommended DFS Versions for Purity Releases” KB and upgrade Purity on the FlashArray and DFS.
  • B. Install the Array and DFS with the Purity that shipped and have Support upgrade remotely.
  • C. Only upgrade the Purity on the FlashArray and then attach the DFS.


Answer : A

Page:    1 / 5   
Exam contains 75 questions

Talk to us!


Have any questions or issues ? Please dont hesitate to contact us

Certlibrary.com is owned by MBS Tech Limited: Room 1905 Nam Wo Hong Building, 148 Wing Lok Street, Sheung Wan, Hong Kong. Company registration number: 2310926
Certlibrary doesn't offer Real Microsoft Exam Questions. Certlibrary Materials do not contain actual questions and answers from Cisco's Certification Exams.
CFA Institute does not endorse, promote or warrant the accuracy or quality of Certlibrary. CFA® and Chartered Financial Analyst® are registered trademarks owned by CFA Institute.
Terms & Conditions | Privacy Policy | Amazon Exams | Cisco Exams | CompTIA Exams | Databricks Exams | Fortinet Exams | Google Exams | Microsoft Exams | VMware Exams